MAIN coalition spox Craig Stevens issued the following statement ahead of Judge Boasberg’s decision
As we await Judge Boasberg’s decision today on the temporary injunction that may halt construction on a portion of the Dakota Access Pipeline, I want to remind you of a few key facts:
- Significant consultation took place with the tribal community throughout the process, and their input was reflected in the final route.
- 389 meetings took place between the U.S. Army Corps and 55 tribes about the Dakota Access project.
- The Standing Rock Sioux Tribe met directly with the U.S. Army Corps nearly a dozen times to discuss archaeological and other surveys conducted to finalize the Dakota Access route.
- Based on input from a number of sources, the pipeline route was adjusted in September 2014 to shorten the pipeline by 11 miles, avoid buildings and other structures, and cross fewer waterways and roads.
- ALSO, project leaders participated in 559 meetings with community leaders, elected officials, and organizations in areas surrounding the Dakota Access Pipeline.
- 43 open houses, public meetings, and regulatory hearings were held throughout 4 states to receive public input.
- The route has been in place for two years, and the section currently being protested is on private land and is part of a pre-existing energy corridor that has had electricity transmission lines and the Northern Border natural gas pipeline.
- This pipeline does not run through the Standing Rock Sioux tribe’s reservation.
- 100 percent of the landowners in North Dakota agreed to construction on their property.
- All requisite permits were filed and approved.
- Concerns about the pipeline’s impact on the local water supply are unfounded.
- In North Dakota, the Missouri River has at least 8 pipelines that already cross it safely carrying hundreds of thousands of barrels of crude product every day.
- The tribe’s water intake is scheduled to be moved by the end by of the year to about 70 miles south of the planned Dakota Access river crossing.
- Once operational the Dakota Access Pipeline would be among the safest, most technologically advanced pipelines in the world.
- There have been multiple archaeological studies of the corridor and no sacred items were found.
- If they turn up, trained archaeologists are on site during construction.
- State archeologists have been on top of this the whole time and “issued a ‘no significant sites affected’ determination in February on the North Dakota segment of the pipeline.
- State archeologists are heading back out to the site, but believe “due diligence under existing regulatory law and regulation was done”.
- Based on the understandable belief that it is doing everything right, the pipeline company has already spent $1.4 billion to develop the pipeline corridor.
- The 1,172 mile project is half complete.
- It has brought hundreds of millions of dollars in investment in heavy equipment and thousands of construction jobs.
- The pipeline would transport petroleum products from the Bakken formation, which supports more than 80,000 North Dakota jobs.