MAIN coalition spox Craig Stevens issued the following statement ahead of Judge Boasberg’s decision

As we await Judge Boasberg’s decision today on the temporary injunction that may halt construction on a portion of the Dakota Access Pipeline, I want to remind you of a few key facts:

  • Significant consultation took place with the tribal community throughout the process, and their input was reflected in the final route.
    • 389 meetings took place between the U.S. Army Corps and 55 tribes about the Dakota Access project.
    • The Standing Rock Sioux Tribe met directly with the U.S. Army Corps nearly a dozen times to discuss archaeological and other surveys conducted to finalize the Dakota Access route.
    • Based on input from a number of sources, the pipeline route was adjusted in September 2014 to shorten the pipeline by 11 miles, avoid buildings and other structures, and cross fewer waterways and roads.
    • ALSO, project leaders participated in 559 meetings with community leaders, elected officials, and organizations in areas surrounding the Dakota Access Pipeline.
    • 43 open houses, public meetings, and regulatory hearings were held throughout 4 states to receive public input.
  • The route has been in place for two years, and the section currently being protested is on private land and is part of a pre-existing energy corridor that has had electricity transmission lines and the Northern Border natural gas pipeline.
    • This pipeline does not run through the Standing Rock Sioux tribe’s reservation.
    • 100 percent of the landowners in North Dakota agreed to construction on their property.
    • All requisite permits were filed and approved.
    • Concerns about the pipeline’s impact on the local water supply are unfounded.
    • In North Dakota, the Missouri River has at least 8 pipelines that already cross it safely carrying hundreds of thousands of barrels of crude product every day.
    • The tribe’s water intake is scheduled to be moved by the end by of the year to about 70 miles south of the planned Dakota Access river crossing.
    • Once operational the Dakota Access Pipeline would be among the safest, most technologically advanced pipelines in the world.
  • There have been multiple archaeological studies of the corridor and no sacred items were found. 
    • If they turn up, trained archaeologists are on site during construction.
    • State archeologists have been on top of this the whole time and “issued a ‘no significant sites affected’ determination in February on the North Dakota segment of the pipeline.
    • State archeologists are heading back out to the site, but believe “due diligence under existing regulatory law and regulation was done”.
  • Based on the understandable belief that it is doing everything right, the pipeline company has already spent $1.4 billion to develop the pipeline corridor.